VB-1742: Plan: plans at four scales: the levy and the plan hierarchy
Status: done (2026-11-25)
Priority: 2
Size: M
Arch: plans
Phase: plan
Design ref: docs/plans/four-scales/README.md (sections 3 and 6); docs/plans/four-scales/levy-custom.md; design.md section 7, Plans at four scales and The levy and own hours; section 9, Outer levies; section 15
Touches: unknown (a plan: design.md and the backlog)
Goal: design.md carries Kim’s decisions of 25 November on how work is planned, and the arch’s implement tasks are written in the path’s order
Acceptance criteria:
design.md carries Kim’s decisions of 25 November: section 7, Plans at four scales and The levy and own hours; section 9, Outer levies; section 15, A controller for any pawn, The API by pawn and body, Decision points and The meeting decides, a holder proposes; and the rows marked “25 Nov” elsewhere, each superseded clause kept as “Was, and stands in the code until the arch plans builds this”.
The reasoning and the evidence: docs/plans/four-scales/README.md (v2 after the mocks; section 3 the design, 3.10 the path and its gate, section 4 the predictions and what would refute them, section 6 Kim’s answers, which govern); docs/plans/four-scales/levy-custom.md grounds the levy’s values; the review that started it, docs/review-jobs-2026-11-25/README.md.
The implement tasks written in the path’s order (VB-1743 to VB-1772) and the wrap-up (VB-1773); the existing tasks the path touches folded in, made to wait or closed (notes below).
Notes:
25 Nov 2026: recorded as done, the plan phase being the design pass of 25 November with Kim; nothing was left for Kim (section 6: all questions answered). Created by the session that wrote the arch’s tasks.
The path (3.10) as tasks. Step 1, repairs: VB-1548 (P1), VB-1597, VB-1689 (folded in), VB-1743 (askFor follows the switch), VB-1744 (wish and propose as verbs). Step 2, a controller per pawn: VB-1745, VB-1746. Step 3, the task as a plan: VB-1747 (the engine and the wood), VB-1748 (the good made at the work), VB-1749 (the carrying kinds; VB-1548’s case falls out), VB-1750 (every other kind), VB-1751 (the phases removed). Step 4, the plan record with authors: VB-1752 to VB-1757. Step 5, partial repair: VB-1758. Step 6, the household’s levy: VB-1759 (design pass), VB-1760 to VB-1765. Step 7, outer levies: VB-1766 (design pass), VB-1767 to VB-1770. Step 8, duties and dated steps: VB-1771, VB-1772. Step 9, aims and personal goods: VB-1781 to VB-1798 (since 25 Nov; it was slice 8’s, a note on VB-188).
The order is held by Waits for: each step’s first task waits for the step before; inside a step, tasks that edit different functions run side by side. The two design passes (VB-1759, VB-1766) are ready now: they edit only design.md.
Every behaviour-changing task carries the gate as criteria; hunger and cost are reported, not gated; tools/same.js only where a task claims no change.
Existing tasks: VB-1553 (standing duties) closed, superseded by VB-1771; VB-1123 (plan mode) waits for VB-1754 and VB-1765, its season bar being the strip’s season zoom; VB-1472, VB-1564, VB-1585, VB-1175, VB-1720, VB-1562, VB-1671, VB-1672, VB-478, VB-315 left as they are, independent (reasons in the arch’s summary).
25 Nov 2026, after the review of the arch’s tasks (25 findings, applied): VB-1774 (the gate as one command, first), VB-1775 (the wood, split from VB-1747, which is now the engine alone and ready), VB-1776 (the rest of the readers of st.player, split from VB-1753), VB-1777 (the chains, split from VB-1754), VB-1778 (the labour budget), VB-1779 (demand and take, split from VB-1763 and put before giving), VB-1780 (the page for steps 7 and 8). Three lanes through steps 2 to 5 (the controller; the methods; the plan record), joined at VB-1754 and VB-1760; steps 6 to 8 serial; VB-1768 and VB-1769 swapped.
25 Nov 2026 (Kim’s answer 21 of README.md, section 6): step 9 of the path, aims and own hours as a livelihood with personal goods pulled forward from slice 8, is this arch’s own; its design pass is docs/plans/four-scales/aims.md (carried into design.md section 7, Aims and personal goods), its tasks VB-1781 to VB-1798 (VB-1781 ready; the rest after the plan record and the levy), and the wrap-up VB-1773 waits for them. It was: “Step 9 is slice 8’s (a note on VB-188)”.
25 Nov 2026, after the review of the aims design: the tasks are VB-1781 to VB-1798 (four split to session size, the clay measure, make or buy, the maker household and the cloth aim added).
25 Nov 2026 (Kim, later the same day): the tasks of aims and personal goods (VB-1781 to VB-1798) were taken out of the backlog and kept for future reference in docs/ideas/aims/; the design (docs/plans/four-scales/aims.md, design.md section 7) stands, and no task builds it now.